YEAR IN REVIEW – 2020

While this past year presented us all with challenges and unforeseen circumstances, Division staff moved forward completing projects and adapting to new ways of doing business. Below are a few of the highlights from 2020.

Coal Program

Coal Program staff helped coal operators navigate the regulatory path nimbly and efficiently to continue their work. Skyline Mine operators determined that additional power was required for continued operations of their long wall miner. A corridor had previously been approved, however a larger corridor for the above ground powerline was needed, requiring additional permitting. Due to time constraints with the onset of winter, staff worked closely with the operator to get the additional permitting finalized so the powerline corridor could be completed.

50’ power corridor 

Deer Creek Mine
Reclamation of the Deer Creek mine was completed in late 2019. During 2020 spring runoff, several rills and gullies began to form on the reclaimed slopes. The operator and program staff immediately mobilized to the site and began working through the regulatory issues associated with repairing the erosion. A rogue culvert unknown during the operation of the Deer Creek Mine was identified as the issue. On-site field visits and conference calls with federal agencies were conducted to address regulatory issues and allow the operator to continue repair work before winter.

Deer Creek reclaimed slope with gully visible
Deer Creek rogue culvert

Minerals Program

Lisbon Valley Mine

On March 20, Division staff was notified that operations at the Lisbon Valley Mine in southeastern Utah had shut down. The Division subsequently issued an order for final reclamation to be complete by September 30, 2021. Over the next several months program staff spent many hours overseeing reclamation operations and reviewing the mine plan and reclamation cost estimate. In January 2021, the operator submitted an adequate bond and obtained Division approval to re-start operations. 

Rock art at Benjamin Quarry

In December 2019, staff issued tentative approval of the revised Notice of Intention (NOI) for the Benjamin Quarry in Utah County. This decision was appealed informally to the Division by concerned area residents and then formally to the Board of Oil, Gas and Mining, which upheld the Division’s decision to approve the NOI with certain conditions. One issue of the appeal included the concern for petroglyphs around the mine.

Staff continue using tablets to record inspections and are working to expand the efficiencies by developing an inspection prioritization application. The tablets help inspectors keep track of inspection frequency, which is a major aspect of determining inspection scheduling.

Abandoned Mine Reclamation Program

Despite a slow and unusual start to the construction season due to the uncertainties presented
by COVID, the Abandoned Mine Reclamation Program (AMRP) completed two coal and six
non-coal abandoned mine reclamation projects this year.

Hiawatha Culvert before

Coal reclamation consisted of the Clear Creek Refuse Reclamation Project and the Hiawatha Culvert Maintenance Project located in Carbon County. Non-coal projects closed a total of 170 hazardous abandoned mines and completed maintenance at 30 previously closed mine openings. Projects included the completion of the Spor Project in Juab County that began in the fall of 2019, the White and Deer Flat Project in San Juan County, Phase I of the Willard Peak Project in Weber County, the Westdip Bat Cupola Project in Tooele County, and the Buckmaster-OIG Project in Emery County. Maintenance projects included the Jacob City Maintenance Project in Tooele County, and the Temple Mountain Maintenance Project in Emery County.

Hiawatha Culvert after

The Hiawatha Culvert Maintenance Project was located about 14 miles southwest of Price at the historic Hiawatha mine. In 1914 mine operators built a culvert over a stretch of Miller Creek to accommodate a road crossing. The 200-foot culvert is constructed of large sandstone blocks and features a rare and striking barrel vault top exhibiting fine craftsmanship representative of the Italian and Greek immigrant stonemasonry of the early 20th century.

In 2012, the Seeley forest fire destroyed much of the vegetation on the Wasatch Plateau above Hiawatha.  As a result, storms washed trees and rock debris down the watershed. Flooding washed out extensive portions of the century-old culvert walls and AMRP staff feared that the unsupported block culvert walls would collapse into the creek.  At best, this would dump sediment in the creek; at worst, the creek could be dammed and risk a catastrophic flood event  Besides losing a remarkable cultural feature and road access across the creek, structural failure of the culvert would have a significant effect on water quality and downstream fisheries.

Last September AMRP staff contracted with Strong Solutions, LLC of Fairfield, Utah to stabilized the damaged culvert by replacing the washed-out portions of the walls and floors with reinforced concrete. Immediately downstream of the culvert, a log jam was removed, and a deep gully head cut that threatened to undermine the culvert was stabilized by building a rock drop structure with stairstep basins to allow fish to migrate upstream.  

Coal mining at Hiawatha began around 1909 and continued until 1992 with extensive operations in four canyons and in multiple coal seams. The company town of Hiawatha, with a peak population of approximately 1,500 residents in the 1940s, supported the operations. 

Oil and Gas Program

The Division’s Oil and Gas Program successfully launched the Field Inspection Prioritization application that uses specific criteria to generate and implement data-driven decisions. Staff has worked with the Groundwater Protection Council (GWPC) to develop and implement the application designed to display in a spatial and report form which oil and gas sites should be inspected according to various inputs. 

All oil and gas wells were given a priority rating from one (highest priority) to three (low priority). Prioritization is based on operational factors such as compliance issues and history, age of the well and how long since the last inspection. Geographic factors include well proximity to surface water, groundwater, human population density and wildlife habitat. 

The program has been operational since January 2020 and has already helped our inspectors increase their inspection efficiency. The field application allows real time data collection that is automatically uploaded to the database saving inspectors time and reducing input errors. The program empowers program staff to consistently make decisions leading to reduced risk and more effective regulation through timely inspections.

This is an effective tool that will give management and staff the ability to make data driven decisions ensuring protection of Utah’s resources, while promoting responsible development.